Project not assigned in Sales Order

Project not assigned in Sales Order

Project Assign Error

MRP RUN does not run due to wrong Sales Order Assigned to Project

 

Raised Issue

·       MRP Doesn’t run from Project Planning Dashboard


Problem Analysis

·       Open Project Planning Dashboard

·       Have a look at Project Error

·       Open BillOfMaterialBean (NOW) and search Suffix column using Work Order; Check import Status

·       Zero is typed instead of “O” in Workorder No. while assigning Sales order under Project

·       Check Project

Solution

Step 01: 

·       Open Sales Order from NOW

·       Change Work Order with Correct Work Order number

·       Save it